Construction & Engineering

Construction Frequently Asked Questions


 

 

 
 
Introduction Virtual Building The Team
Services Clients Articles
    Latest News
    Publications
    Registration Form

 

1. My contractor is due to start on site next week and I have been given a building contract to sign. It's a JCT. Is that okay? >>more>>

2. The Architect, Engineer and Surveyor are working as a team. I haven't had any contact with the Engineer. Is that okay? >>more>>

3. What is a collateral warranty? >>more>>

4. I'm a tenant. Why do I need a collateral warranty? >>more>>

5. What about the Third Party Rights Act - doesn't that give me some rights? >>more>>

6. The contract completion date was May, the Architect says that has now been postponed to July. What can I do about this? >>more>>

7. The price in the contract was £x. I have paid that already and they are nowhere near finished. What is this going to cost me? >>more>>

8. The contractor is nearly finished and I want to get into the building to sort out the interior fittings. The Architect and Contractor are being awkward about this. Why? >>more>>

9. The building works were completed 12 months ago and the contractor is being difficult about coming back to do the snags. What should I do? >>more>>

10. The contractor has just gone bankrupt. The job is half finished. Help! >>more>>

11. I don't agree the Architect's latest certificate. It's more than the contract price. Should I pay it? >>more>>

12. I am the contractor. The architect is ignoring my legitimate claim for loss and expense. What should I do? >>more>>

13. Adjudication - what's that? >>more>>

14. Great! What do I do to start an adjudication? >>more>>

15. How do I get an adjudicator appointed? >>more>>

16. What next? >>more>>

17. Do I need a lawyer? >>more>>

18. I have the adjudicator's decision. It's wrong. What can I do? >>more>>

19. I am the contractor. Should I start work on the back of a Letter of Intent? >>more>>

20. I am reorganising my contractor group of companies. Can I transfer my existing contracts to the group company which will now carry on this type of work? >>more>>

 

 

1.My contractor is due to start on site next week and I have been given a building contract to sign. It's a JCT. Is that okay?

JCT stands for Joint Contracts Tribunal. The JCT is a committee of people who represent most of the interest groups involved in the construction process. The JCT produce a number of standard form building contracts which they hope are reasonable and fair to the parties involved. A JCT contract will usually be a good starting point but to know if it is "okay" for your project we would need to know more about the scheme and the risks you are prepared to take primarily in terms of design, control, cost, time, etc.

 

2. The Architect, Engineer and Surveyor are working as a team. I haven't had any contact with the Engineer. Is that okay?

It depends. If you haven't met or written to him at all he is probably working for the Architect. Check the Architect's appointment to see if it mentions engineering services. It is usually better practise if the Engineer and Surveyor are appointed directly by you.

3. What is a collateral warranty?

It's a contract between anyone with an interest in a development (typically a tenant, fund or purchaser) and someone responsible for the construction of that development (typically an architect, engineer, quantity surveyor, contractor or subcontractor). The person giving the warranty "warrants" that it will properly perform its contract for the construction of the building. If there is a problem with the completed structure the warranty may be used to claim damages from those responsible.

4. I'm a tenant. Why do I need a collateral warranty?

If there is a problem with the building you may have to repair it under the terms of a repairing covenant in your lease. If you have warranties from the designer and contractor you may be able to recover reasonable repair costs and other foreseeable losses (e.g. loss of income) caused by the failure. If you have no warranty it is unlikely that you will be able to claim.

5. What about the Third Party Rights Act - doesn't that give me some rights?

Most standard form contracts expressly exclude the operation of the Act. People prefer to rely on the certainty of contracts. If the Act applies, it will only give you rights if there is some evidence that the contracting parties intended this. There is some uncertainty about how this will be proved.

6. The contract completion date was May, the Architect says that has now been postponed to July. What can I do about this?

Most standard form contracts allow for some flexibility in the completion date. If May really is a "drop dead date" you need non standard provisions in the contract, which should be drafted by a solicitor.

If you didn't get special completion provisions drafted, delays caused by adverse weather, variations and additional works will usually be your risk. The contractor will get an "extension" of the time he has to complete the job. If you have caused the delay the Contractor may also be entitled to recover costs associated with this extra time on site.

If the contractor is late for reasons, particularly where he has been inefficient, he may have to compensate you for the delay. Most standard form contracts provide that the contractor must pay liquidated damages at a weekly rate. Talk to your architect about whether these should be deducted from the next valuation payment. If you want to proceed, check the contract provisions and follow them to the letter. The onus is on you, not the Architect to send notices etc. If in doubt, take legal advice.

7. The price in the contract was £x. I have paid that already and they are nowhere near finished. What is this going to cost me?

Discuss this with the design team and the contractor. There may be any number of reasons why this project is costing you more than originally anticipated. If you want any changes to design get them costed by the surveyor and the builder before going ahead. If you want a guaranteed maximum price say so at the outset and get some legal advice on how to ensure you have a binding commitment from your construction team. You may need legal advice on amendments to the standard form contracts.

8. The contractor is nearly finished and I want to get into the building to sort out the interior fittings. The Architect and Contractor are being awkward about this. Why?

Most standard form contracts do not allow you to occupy the building for any purpose until it is finished. The Architect may be worried because your tradesmen could disrupt the contractor's progress. If this disruption causes extra cost or delay, you will have to compensate the contractor.

Also, if your consultants are checking the work to see that it is complete, the fit out works may make that task more difficult. Discuss this with the contractor and the architect. Perhaps you can have limited access to specified areas or at particular times without this having any impact on progress?

It is not in your interests to pressure the Architect to certify practical completion when the works are not really finished. This is particularly unwise if you have a performance bond which lapses on practical completion.

9. The works were completed 12 months ago and the contractor is being difficult about coming back to do the snags. What should I do?

Check the contract. Have you issued a snagging list in the way it describes? If so, there is usually a procedure whereby you can give notice then carry out the works using another contractor. You can deduct the cost from the retention. If you are unsure about the procedure or the work will cost more than the retention, take legal advice.

10. The contractor has just gone bankrupt. The job is half finished. Help!

Don't panic! First find out exactly what has happened to the contractor. Perhaps an Administrative Receiver has been appointed who wants to finish the job. If so, ask him for his detailed proposals and consider them carefully with your advisers. If a liquidator has been appointed he will not continue the works but he may well introduce you to someone who will. Don't dismiss such proposals out of hand; the liquidator doesn't want you to spend money unnecessarily either. Consider approaching the firms on your original tender list. Take legal advice on any contract to complete the works and any further payments to the contractor or any nominated sub contractor. Follow the contract procedures about termination and sorting out the final account.

11. I don't agree the Architect's latest certificate. It's more than the contract price. Should I pay it?

If you are convinced the works are not properly valued and determined not to pay you only have a few days to write to the contractor setting out your reasons for non payment. (The exact time limit should be in the contract. If not, you have 5 days from the date of the certificate):

1. Write a letter to the architect explaining your concerns. Remember he has to act independently. Do not try to bully or threaten him.

2. Consider taking a second opinion on the costs certified. Take legal advice before embarking on this process.

3. If you do not pay the certificate there is every likelihood that the contractor will suspend work and start an adjudication. Unless you are prepared to deal with the consequences, pay this valuation and work closely with the design team to understand their professional advice. Take legal advice.

12. I am the contractor. The architect is ignoring my legitimate claim for loss and expense. What should I do?

Has he given you an extension of time (with reasons)? If not, press him for this first step. If you have the extension, point out that you will be claiming finance charges for the period from the date when losses were incurred to when they were paid. Send him a calculation. If all else fails, go to adjudication.

13. Adjudication - what's that?

You have the right to refer all disputes under construction contracts to an adjudicator. He or she must decide the dispute within 28 days of his appointment.

14. Great! What do I do to start an adjudication?

Check your contract for procedure. You will need to serve a notice. It is a good idea to get the notice checked by a solicitor who will make sure it properly describes the dispute. If the description is too vague, narrow or wrong this could lead to problems with enforcement.

15. How do I get an adjudicator appointed?

Check the contract. If it doesn't say anything then you can go to a number of professional bodies who will select an adjudicator for you. Think about what professional background you think the adjudicator should have. You will have to pay a fee for the appointment.

16. What next?

The adjudicator will probably suggest a procedure. If you think his procedure is not fair, say so and explain your view. However, at the end of the day you should comply.

17. Do I need a lawyer?

It depends on your claim/defence. If there are difficult legal issues solicitors will be well placed to help. If you think there is a serious injustice in the procedure take legal advice before the adjudicator's decision is due.

18. I have the adjudicator's decision. It's wrong. What can I do?

Is it a mistake? If so, write to the adjudicator immediately to tell him you think he has made a mistake. If you do this quickly enough (perhaps within hours), the adjudicator may issue a corrected decision.

Is it wrong/unfair? Take legal advice in good time before the decision is due for payment. However, in most cases the decision will be enforceable. If you want to take the issue further you will have to consider litigation or arbitration.

19. I am the contractor. Should I start work on the back of a Letter of Intent?

Letters of Intent are common, but what actually does it say and is it legally binding? Is the Letter to cover a short period while agreed contract documents are circulated for signing or are there major contract terms still to be agreed? You may be authorised to spend up to a stated amount under the Letter but what about loss of profit claims and discontinuance costs if a Contract is never signed? Don’t run the whole job on the back of a Letter of Intent.

20. I am reorganising my contractor group of companies. Can I transfer my existing contracts to the group company which will now carry on this type of work?

This is not straightforward and detailed legal advice needs to be obtained. For example even if the Contract permits assignment of the rights and benefits under contracts, obligations cannot normally be transferred without the Employer’s or sub-contractors consent. There may be other issues such as continuing P.I. cover for contracts involving contractor’s design, and changing bonds and dealing with retentions.